| 1 |
The Royal Society of
Edinburgh (RSE) is pleased to respond to the Scottish Parliament
Enterprise and Culture Committee Inquiry into the future of the
renewable energy sector in Scotland. This response has been
compiled by the General Secretary, Professor Andrew Miller and
the Research Officer, Dr Marc Rands, with the assistance of a
number of Fellows with considerable experience in this area. |
| 2 |
The large role
suggested for renewable energy by the Scottish Executive, as
much as 40% of electricity by 2020 is laudable, but may not be
able to be achieved and the real engineering analysis and cost
of this possibility has yet to be assessed. |
| 3 |
Scotland is
fortunate in having a lot of the basic resources for wind, wave,
tidal hydroelectric and even solar energy. However, the present
2% of electricity in the UK generated from renewables is largely
from the medium-to-large size hydroelectric plants, many of
which are in Scotland. Given that present levels of
hydroelectric generation took decades to install, doubts must
exist over the possibility of installing more than double that
capacity in other renewable energy forms in the time scales
proposed, and perhaps the most practical application would be to
meet relatively small local demands. |
| 4 |
Some of the issues
identified by the Inquiry are now addressed below: |
|
What
are the current barriers, and what action needs to be taken to
ensure that the targets are met? |
|
Wind
Energy |
| 5 |
At present, if all
the wind farms currently operating in the world were to be put
on the South Downs, they would generate only 15 per cent of UK
electricity, less than the aspirational target for the UK alone
for 2020. To produce 20% of UK electricity, largely from wind,
would require twenty, 2MW machines to be installed every week
between now and 2020. The Danes are just completing the Horns
Rev offshore field 11km out into the North Sea, and using the
latest technology they have succeeded in installing one machine
every two days. To achieve something similar in Britain, a huge
capital investment programme to provide the necessary offshore
infra-structure will need to be mounted, but there will be
problems in getting the private sector to pay for this unless
substantial price guarantees can be made. For example, the
floating cranes necessary to install at a rate of 60 machines
per week offshore will have to be built and the necessary
undersea cabling installed. |
|
Solar
Energy |
| 6 |
Solar energy could
be a good option if new, more efficient, cells can be produced
and introduced into small factories and houses as a boost to
grid energy. Similarly, wind power offers potential, with
offshore winds offering promise for both technical (more
sustained and powerful airflows) and environmental reasons (less
visual intrusion and effect on landscapes). The building of new
hydro plant will be limited due to difficulties in obtaining
planning permission and large land-based wind farms are likely
to experience similar problems. |
|
Fuel Cells |
| 7 |
In terms of fuel
cells, the UK has a poor record in industrial take-up of these
cells, but quite a good record of university research. The
central problem has been that the low industrial interest has
inhibited both the Department of Trade and Industry and
Engineering and Physical Sciences Research Council from
investing in the type of long-term R&D really necessary in
this type of technology. There have been several initiatives
that have petered out. Relevant departments in universities such
as Imperial, Oxford, Newcastle, Loughborough and Keele have been
encouraged to set up fuel-cell groups only to find funding has
evaporated, and the groups have, inevitably, moved on to other
areas. Only if funding agencies are prepared to give substantial
long-term commitments to R&D will the UK really develop the
leading edge technologies needed in this area. |
| 8 |
The main thrust is
towards hydrogen-based fuel cells, which obviously pre-supposes
that sustainable sources of hydrogen can be identified, and the
hydrogen stored efficiently; but neither is straightforward.
Sustainable sources of hydrogen could include biomass which is
very expensive, or photovoltaic-driven electrolysis of water.
The latter urgently needs research, as the last serious
investigations were funded by the space agencies in the 1980’s
in order to develop bipolar cells for satellites. Both cell
designs and catalysts are, however, far from optimised. In
addition, the cost of electrolytic hydrogen is some 4-7 times
that of hydrogen derived from cracking making it an expensive
fuel. Storage is also a major problem. There are various
methods, from high-pressure storage, through absorption into
metal alloys or into special forms of carbon, that have been
proposed and tried, but, especially for transport, such methods
all carry major penalties in either weight or low-temperature
requirements. |
| 9 |
The essential
feature of fuel-cell research is that there are two major
difficulties: the costs of the fuel cell itself, and the costs
and complexity of the systems engineering required to fabricate
a working device. The main costs of a low-temperature
hydrogen-oxygen fuel cell are the catalysts (though this is no
longer a major problem with modern electrode design) and the
costs of the membrane (a perfluorinated sulphonic acid polymer
which is difficult to synthesise, and is mainly used by the
chlor-alkali industry). Modern membrane-electrode assemblies can
be fabricated for a few hundred dollars per kilowatt installed
power, but this remains high compared to current technologies.
In the case of high-temperature fuel cells, the main
difficulties are encountered with materials chemistry and
engineering; attempts have been made to synthesise lower
temperature electrolytes to reduce the materials difficulties,
but catalyst costs then begin to rise. |
| 10 |
For both types of
cell, however, the systems engineering remains extremely
expensive, partly because there are no economies of scale yet
realised, and partly because there are, as yet, no standard
solutions agreed upon. There is almost no indigenous fuel-cell
industry in the UK, and no prospects of one developing unless,
as indicated above, there is the guarantee of really long-term
funding. There is critical mass in the universities, at least in
the science and electrical and power engineering areas, but
there is a lack of electrochemical engineering that is extremely
serious. |
|
Wave
and Tidal Energy |
| 11 |
The concepts for
generation from wave and tidal resources are quite
well-developed, but the technology is not yet mature for either.
Water-based technologies have an advantage over wind and solar
in that the energy flux is an order of magnitude higher,
typically 4kW per metre squared compared with 400W, and often
much less for wind and solar technologies. Modern load
management techniques have also substantially alleviated earlier
intermittent load fluctuating problems pertaining to both tidal
and wave power among other renewable sources. However, factors
relating to system integration still have to be considered even
now for both tidal power and wave power. Wave energy converters
need hydrodynamic characteristics to enable them to operate at
maximum efficiency over the normal range of sea conditions, yet
they must be robust enough to withstand the worst storms.
Despite its large potential resource for the UK of 40-50 TWh/year
(approximately 15-20% of UK electricity generation output), no
economic large scale wave energy device has yet been produced,
and load management and integration problems are still quite
severe. |
| 12 |
The most likely
sources of wave energy are on the West coast of Britain, and at
some considerable distance from likely large users of
electricity. Hence the total costs for design and erection of
the energy generators, and the power transmission system must be
analysed and estimated in relation to the market, and the price
which the market will pay. Too often in the past, seemingly
attractive projects have foundered because of over-optimistic
initial assumptions. The problem of grid connection is common to
all renewable sources as distribution grids tend to be
"tapered" towards their periphery, which is often
where the renewable energy is available. The intermittent nature
of the supply also puts it at a disadvantage with the New
Electricity Trading Arrangements (NETA) under which fluctuating
supply attracts a penalty. |
| 13 |
The economic
advantage of wave and tidal power will also depend upon the
relative values of imported and exported energy and on the
ability of the supply system to meet the pumping demand. It will
be difficult for either to become commercially viable if the
present economic indicators continue to be used. However, if a
new approach is taken to assess the value of renewable
resources, then viability may become possible. Recent moves
towards 'green credits' are moves in the right direction but
more could be done. These new arrangements require suppliers to
provide 10% of their supply from renewable sources by 2010 or
pay a penalty. However, at present the price of electricity
produced by wave and tidal stream technologies comes in at above
5p per unit (the capped price of the renewable electricity to be
supplied in this arrangement). It will be difficult, therefore,
to see why electricity suppliers should enter into such
contracts with wave and tidal power providers when they can buy
themselves out at 5p per unit. In addition, tidal stream energy
is not included in the Renewable Obligation list of acceptable
technologies despite its potential. |
| 14 |
The main wave energy
project is a shoreline device, now called Limpet, on the Island
of Islay and is run jointly by WaveGen and Professor Whittaker
from Queen's University Belfast. It operated successfully for
ten years and has now been superseded by the Mk2 device which
has been operating since November 2000 and generates 500kW.
While the concept has been proven, it is onshore and so limited
in power rating and it requires specific shoreline
characteristics. A significant problem has also been in
transmitting the power to the grid, with the existing grid line
to the main land requiring significant and costly strengthening.
In terms of tidal stream energy, the science is well understood
but the technology requires further development. One 300kW unit
is being installed by Marine Current Turbines of Lynmouth in
Devon and The Engineering Business has also demonstrated a small
model device which they are seeking to upgrade to a
demonstration stage. |
|
Biomass
Fuels |
| 15 |
Fuels of biological
origin are making a substantial contribution to the reduction of
use of fossil fuels in combined heat and power systems in some
countries in Europe; for example Sweden. A more extensive use of
biofuels in combined heat and power schemes could make a
significant contribution to a basket of measures. Suitable
biofuels include residues from normal forestry management
operations and purpose-grown short rotation forest crops.
Worldwide, an increasing number of sawmills, wood pulp plants
and composite board plants utilise the residues resulting from
their processing operations to provide energy and are thereby
self-sufficient for heat and power and, in some cases, export
electricity. |
| 16 |
Purpose grown, short
rotation forest crops (willows and poplars in particular)
contribute a significant amount of energy in combined heat and
power schemes in Sweden and Finland and with the expansion of
such schemes in the UK they could also make a significant
contribution. The problems which will arise when enlarging pilot
operations to areas of approx. 2000 ha of land and power
stations of more than 10 MWe will concern land ownership,
continuity of supply from hundreds of farmers and competition
for the feed stock from pulp and board mills. There are,
however, a range of crops suitable; for example Willow, Poplar
and Miscanthus (Elephant grass). Further work is required in
developing these annual crops. |
| 17 |
It is estimated that
the theoretical energy cropping and forest residue resource in
Scotland could contribute around 2.3 GW of electrical generating
capacity. However, taking planning, cost and other electrical
infrastructural factors into account, the actual resource may
only be around 170 MW. More detailed research on the potential
for short-rotation coppice alone suggests that whilst there is a
theoretical potential for some 500 MW biomass-to-energy plants
if all the suitable land was converted to coppice, a more likely
scenario would be around 20-25 MW biomass-to-energy plants in
Scotland, assuming a 5% take up by farmers on suitable land. If
one assumes that, for the foreseeable future, patterns of
electrical energy consumption in Scotland remain the same (i.e.
peak demand around 5.6 GW) then biomass-to-energy projects will
not contribute significantly (<3%). They are therefore likely
to be only a minor element in achieving the UK government's
policy objective and ranked third behind wind and hydro. |
|
Environmental
Factors |
| 18 |
It should be noted
that some renewable forms of generation also have the potential
for quite severe environmental impacts (as previously reported).
Wave power devices, for example, impinge on coastal
environments, tidal barriers affect habitats and cause change,
wind farms pose threat to bird life and cause major visual
pollution, and even hydro can affect wildlife and river form.). |
|
The
implications for the reliability of supply if the Executive’s
aspirational target is met? |
| 19 |
Wave, wind and solar
power are all subject to intermittency of supply, and
necessitate substantial use of conventional standby plant
operating for much of the time at less than optimum efficiency
on part-load. Accommodating any intermittent electricity source
into the grid distribution system presents considerable
technical and cost problems which should not be underestimated.
Denmark, with around 15 per cent of wind electricity on its
distribution grid, has just removed subsidies for three proposed
150MW offshore wind farms, as any more wind power would have
caused serious destabilisation of their grid. |
|
What
action needs to be taken to ensure that the targets are met? |
| 20 |
Some important
milestones that will need to be met to achieve the Executive's
aims will be: |
|
| - |
Speeding up
the planning permission process without "short
circuiting" or damaging the democratic process. |
| - |
Financially
incentivise the distribution network operators to make
it attractive for them to connect renewable generators
to their systems. At present they have no financial
incentives to connect new renewable generation. One
result of this is that individual developers are
experiencing serious difficulties in negotiating with
the relevant distribution network operator relating to
connection of their plant. Network operators are also
generally wary of connecting large volumes of renewable
generation. |
| - |
Plan and
develop future high voltage transmission network
extensions in a way that allows the large volumes in
remote areas, e.g. Northern Scotland, that are foreseen
to be provided with access to the high voltage grid. |
| - |
Given that
all forms of renewable generation are currently
uneconomic compared to more conventional sources look
again at the Renewable Obligation Certificate (ROC)
arrangements in a way that will ensure that investors
will not lose money if the value of these falls in the
future, as seems likely. ROCs have a par value of 3p/kWh
and are currently trading at say 5p/kWh, but as a
marketable commodity. If they fall below
"economic" levels, investors will depart the
scene and this will impact upon future development as
all new large wind farms being built today are being
developed by large companies on their own balance
sheets. |
|
| 21 |
Some other
suggestions might also include: |
|
| - |
Given the
large number of people and organisations engaged in the
debate, an Annual Report of progress toward the
Executive's target of 18% renewable electricity by 2010
could be published, with reasons given for exceeding or
falling short of the intermediate targets. It should
also make clear what premium industry and the public are
paying for the benefits that arise from renewable
generation, including the cost of standby generation and
of the necessary modifications to the electrical power
system infrastructure. |
| - |
All serious
technological competitors in the renewable generation
field, such as wave energy and biomass crops, should be
able to point to at least two demonstration projects so
that confidence can be gained by those considering
similar commitments. |
| - |
Many of
those currently promoting renewable energy projects are
small companies who seem to have no common agenda or
technical affiliation to one another, or are unaware of
all the issues involved in developing their projects.
The DTI and Ofgem have found it difficult to engage this
small generator community in debate and although each
technology seems to have a "technical society"
there needs to be some kind of "trade
association" to look at the wider issues. |
|
| 22 |
One major casualty
of the privatised energy market has been research and
development. The world-renowned research carried out by the
Central Electricity Generating Board and the Gas Council in the
1970s and 1980s has been abandoned by the privatised energy
companies. While the Government has stimulated research in
renewables, a comprehensive energy supply research programme
needs to be put in place. Some urgent topics, in particular,
would include: carbon sequestration; electricity/energy storage;
hydrogen for transport; restructuring the grid system to
accommodate embedded generation and the financial and stability
implications; and the new gas supply infrastructure to provide
for importing large quantities of gas. While some of these
topics are being addressed by a variety of bodies, co-ordination
is poor, with Westminster's Environmental Audit Committee
identifying 23 different grant giving bodies in this area. |
|
Additional
information |
| 23 |
In responding to
this inquiry the RSE would like to draw attention to the
following Royal Society of Edinburgh responses which are of
relevance to this subject: Energy and the Environment (December
1998); New and Renewable Energy (May 1999); Non-Food
Crops (May 1999); Wave and Tidal Energy (February
2001). |
Professor Andrew Miller
General Secretary
Royal Society of Edinburgh
22-26 George Street
Edinburgh EH2 2PQ |